Pipeline Diversion for Foynes to Limerick Road (including Adare Bypass)

Overview

As the national body responsible for the country’s gas network, we are occasionally required to facilitate diversions of the gas pipeline network to support major new public and private infrastructure developments of significant economic or social value.

One such development is the new 35km Foynes to Limerick Road (including Adare Bypass) project, where the road scheme conflicts with our transmission (high-pressure) pipeline that runs from Dublin to Galway, called ‘Pipeline to the West’.

Limerick City and County Council has requested pipeline diversions at the two conflicting locations to facilitate safe construction of the road scheme.

Summary of works to be completed:

  • A 439m long diversion of ‘Pipeline to the West’ at Rinculla, near Foynes, Co. Limerick
  • A 256m long diversion of ‘Pipeline to the West’ at Croagh, near Rathkeale, Co. Limerick
  • Temporary bypass pipelines for both diversions to maintain gas flows to customers
  • Protection of the pipeline at six other locations by installing reinforced concrete slabs

Construction got under way at both diversion sites in November 2026, and is due to be completed in late 2027.

We are supported in delivering this important work by our design engineer partner Tetra Tech and our construction delivery partner, Murphy.

Large steel pipeline sections during construction with an excavator.

Project update

Construction works for the two pipeline diversions commenced at both sites, in Rinculla and Croagh, in November 2026. To ensure these works are delivered efficiently, our crews will work simultaneously between locations.

Project works will include:

  • Construction of 439m of new 750mm diameter, welded steel transmission (high-pressure) pipeline at Rinculla, near Foynes, Co Limerick.
  • Construction of 256m of new 750mm diameter, welded steel  transmission (high-pressure) pipeline at Croagh, near Rathkeale, Co. Limerick.
  • Construction of temporary bypass pipelines to maintain gas flow to customers during the connection of the new diversions to the existing pipeline.
  • Stopple operations utilised at each connection point, with  specialist equipment and temporary valves used to isolate the gas for the diversion connections while also facilitating gas flows on the temporary bypasses.
  • Testing and commissioning of the new pipeline diversions.
  • Decommissioning of redundant sections of the existing pipeline.
  • Reinstatement works following construction.

All these works will be carried out while maintaining supply to the downstream network, ensuring citizens and businesses do not experience any interruptions to their gas supply.

Environment and planning

This project – referred to as the Foynes-Limerick Pipeline Diversions - was granted a Section 39A Consent (“Consent”) from the Commission for Regulation of Utilities (CRU) on 9 April 2026 following technical and environmental review. 

An Appropriate Assessment (AA) Screening Report was completed for the construction of the pipeline diversion to determine whether the proposed works were likely to have significant effects on designated European sites. 

An Environmental Impact Assessment Screening Report (EIAR) was also completed for the construction of the pipeline diversion to determine whether the proposed works were likely to have significant effects on the environment.

The S39A Consent documents including all environmental reports are available to view at: https://www.cru.ie.

What is a pipeline diversion?

Transmission pipeline diversion projects are required when a third party needs to complete construction or developmental works over land where gas pipelines are located. This involves Gas Networks Ireland moving or altering the gas pipeline route so that it is safe to proceed with construction. 

The requestors can be a public or private organisation and this work is key to supporting economic and social progress because the works are generally linked to new national or commercial infrastructure projects such as factories or motorways. 

Timelines on these projects are usually critical to avoid delivery delays. These projects are entirely funded by the requestor.